EDGEWOOD, PENNSYLVANIA - A GREAT
COMMUNITY!
|
|
Parkway
Construction Delays, including Edgewood
Avenue Detour
I-376 Section A38 - Parkway
East Edgewood / Swissvale to Churchill.
The project limits are between the
Edgewood/Swissvale Exit and SR Business
Route 22 Exit on the Parkway East.
It is contractor’s intent to start the
construction phase of this project on March
31, 2008 and continuing thru November 30,
2008. The majority of the work is performed
on weeknights and weekends.
March 31st to April 4th
- During the first week of April, work will
begin on Braddock Avenue between the hours
of 7 pm and 6 am. Parking will be
redistricted from 6 pm to 6 am. This work
will consist of new pavement placement on
Braddock Avenue between the Parkway ramps
and the City of Pittsburgh border. Braddock
Avenue will be restricted to a single lane.
Work will also begin on the West, or inbound
side of the 376 Parkway East during the
hours of 9 pm to 5 am to perform concrete
roadway work and other miscellaneous
operations.
April 4th & 5th - Starting the
weekend of April 4, 2008 at 9 pm, Trumbull
Corporation intends to close the West, or
inbound side of the 376 Parkway East between
Churchill and Edgewood / Swissvale to
perform various concrete operations.
-
Detour
- In place
from the Churchill exit, down Penn
Avenue to Braddock Avenue. After turning
left on Braddock Avenue, the detour will
continue down to the Parkway ramps in
the boroughs of Swissvale and Edgewood.
Also during the weekend of
April 4, the contractor intends to close
Edgewood Avenue over top of the parkway to
perform various concrete structure and deck
repairs.
-
Swissvale Side Detour
- Use Edgewood Avenue to
Columbia Avenue, then Westmoreland
Avenue, to South Braddock. After
reaching South Braddock Avenue the
detour takes motorist past the Edgewood
Town Center to Greendale Avenue. Take
Greendale Avenue to Race Street. Race
Street takes motorist back to Edgewood
Avenue.
-
Edgewood
Side Detour - Use
the same routes in reverse except for using
West Swissvale Avenue from Race Street down
to South Braddock Avenue.
During the next several weeks,
the contractor will continue to have nightly &
weekend operations on the Parkway during the 9
pm to 5 am hours during the week and
continuously on the weekends; lane restrictions
during week days and closures implemented on
weekends.
Go to the Project Website (I376 Section A38)
www.penndot11.com for up-to-date information
relating to the project. This site will be in
operation beginning March 24th. |
|
RETURN TO TOP |
|